Home » Posts tagged 'kiran morzaria'

Tag Archives: kiran morzaria

Cadence Minerals #KDNC – Azteca Refurbishment Complete. Mechanical completion achieved; commissioning scheduled next week

Cadence Minerals plc (AIM: KDNC) announces that refurbishment of the Azteca processing plant at the Amapá Iron Ore Project is complete, with mechanical completion achieved on 3 September 2026. The plant now moves into commissioning. Commercial operations and shipments remain subject to successful commissioning and receipt of the operating licence (Licença de Operação) for Azteca (the “Operating Licence”).

Highlights

  • Mechanical completion achieved: Refurbishment finished on 3 September 2026. All eight plant systems are complete.
  • Execution delivered: Azteca advanced from approximately 48% completion on 2 July 2026 to mechanical completion on 3 September 2026.
  • Commissioning next: Cold commissioning is scheduled to start next week. Wet commissioning will follow, with hot commissioning subject to completion of the applicable regulatory requirements.
  • Safe delivery: No safety incidents were recorded during the reporting period.
  • Remaining gates clear: Commercial operations and shipments remain subject to successful commissioning and grant of the Operating Licence.

Kiran Morzaria, Chief Executive Officer, commented: “Mechanical completion closes the refurbishment phase. The next job is to prove the plant through commissioning.

We will progress sequentially through cold, wet and hot commissioning, identifying and resolving issues as they arise. Commercial operations and shipments remain dependent on successful commissioning and grant of the Operating Licence.

Azteca is intended to establish the first production and cash-flow platform at Amapá. Successful delivery would move the project from refurbishment into operations and support the wider redevelopment strategy.”

Execution Update

All eight plant systems are complete: the hopper/feed system, transfer conveyor, screen, process tank, magnetic-separation circuit, piping, spiral concentrator and electrical system. The Company recorded no safety incidents during the reporting period.

Regulatory Position

The previously granted installation licence (Licença de Instalação) (the “Installation Licence”) authorised the refurbishment and installation works now completed at Azteca. DEV has submitted its application for the Operating Licence to SEMA/AP.

DEV is permitted to undertake cold and wet commissioning. Hot commissioning remains subject to completion of the applicable regulatory requirements.

Grant of the Operating Licence remains required before commercial operations and shipments can commence.

Next Steps

Cold commissioning is scheduled to start next week. The completed equipment, electrical distribution and control systems will be tested without ore. Completion of this stage will allow the programme to move into wet commissioning.

Wet commissioning will introduce process water and trial material through the wet circuit. Following completion of this stage, hot commissioning will commence once the applicable regulatory requirements have been completed.

Hot commissioning will involve limited processing of run-of-mine material to tune plant grade and recovery. Any concentrate produced during this stage will be stockpiled. Commercial operations and shipments will remain subject to successful completion of commissioning and grant of the Operating Licence.

Cadence Ownership

As of 31 May 2026, Cadence’s total investment in the Amapá Project was approximately US$16.1 million. Cadence holds a 36.2% equity interest in Pedra Branca Alliance Pte Ltd (“PBA”), which owns 100% of DEV Mineração S.A. (“DEV”), the owner and operator of the Amapá Project.

About the Amapá Project

The Amapá DR Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, Azteca is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to successful commissioning, completion of related regulatory workstreams and receipt of the Operating Licence.

For further information, contact;

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Matthew Diaz-Rainey

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608
Alan Green               

 

Qualified Person

Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.

Cautionary and Forward-Looking Statements

This announcement contains forward-looking statements. Such statements are based on the current expectations, assumptions and beliefs of the Directors and are subject to known and unknown risks and uncertainties. Forward-looking statements are not guarantees of future performance and may often be identified by words such as “believe”, “expect”, “intend”, “may”, “plan”, “should”, “will”, “could” and similar expressions. Actual results may differ materially from those expressed or implied by such statements due to a range of factors, many of which are outside the control of the Company, including changes in economic conditions, market conditions, regulatory developments, the actions of governmental authorities, the availability of funding and other risks affecting the Company’s operations. Readers should not place undue reliance on forward-looking statements, which speak only as at the date of this announcement. Except as required by law or applicable regulation, the Company undertakes no obligation to update or revise any forward-looking statements.

Cadence Minerals #KDNC – Azteca Refurbishment Update

Refurbishment 97% complete and ahead of plan as of 22 August; Operating Licence application submitted

Cadence Minerals plc (AIM: KDNC) announces that, as of 22 August 2026, refurbishment of the Azteca processing plant at the Amapá Iron Ore Project had reached 97% weighted physical completion, compared with 95% planned and 87% reported on 10 August 2026.  The Company continues to target completion of the refurbishment works by 31 August 2026. In parallel, DEV Mineração S.A. (“DEV”), the Brazilian operating company for the Amapá Project, has formally submitted its application for the operating licence (Licença de Operação) for the Azteca plant (the “Operating Licence”) to the Amapá State Environmental Secretariat (“SEMA/AP”).

Once the refurbishment is complete the plant is intended to progress into integrated commissioning. Commercial operations and shipments remain subject to successful commissioning and receipt of the Operating Licence.

Highlights

  • Ten-point advance: As of 22 August 2026, weighted physical completion was 97%, compared with 95% planned and 87% reported on 10 August 2026.
  • Critical path moves ahead: Electrical installation advanced from approximately 69% to 95%. The principal execution constraint identified in the previous update is now ahead of schedule.
  • Core processing systems delivered: The hopper/feed system, transfer conveyor, screen and process tank are complete. Magnetic separation and piping are approximately 99% and 98% complete, respectively.
  • Final close-out underway: The remaining work is concentrated in technical handovers, spiral concentrator completion, electrical panels and final equipment connections.
  • Commissioning next: The programme continues to target completion of the refurbishment works by 31 August 2026 before progressing into integrated commissioning.
  • Operating Licence: DEV Mineração has submitted its application for the Azteca operating licence to SEMA/AP.

Kiran Morzaria, Chief Executive Officer, commented: “Execution is what matters. Azteca moved from 48% to 77%, then to 87%, and reached 97% by 22 August.

Electrical installation was the principal execution focus. It has advanced to 95%, moving from behind the mechanical workstreams to ahead of plan.

At that reporting date, the remaining work was defined: close the technical handovers, complete the spiral concentrator and electrical panels, connect the equipment and move into commissioning.

Our focus is clear: complete the refurbishment against the 31 August target and maintain execution discipline through commissioning. Successful commissioning and the Operating Licence remain the gateways to commercial operations and the first operating platform at Amapá.”

Execution Update

As of 22 August 2026, the refurbishment programme was 97% complete against 95% planned. This represented a ten-percentage-point advance from the 87% reported on 10 August 2026

At that reporting date, 58 of the 64 identified activities had been completed. The remaining six are in progress.

The hopper/feed system, transfer conveyor, screen and process tank are complete. Magnetic separation has reached approximately 99% completion and piping approximately 98%. The spiral concentrator has reached approximately 85% completion, compared with approximately 78% planned.

Electrical installation advanced from approximately 69% to 95%, compared with approximately 87% planned. Electrical works were the principal execution focus on the previous update. That workstream is ahead of plan.

The remaining work is specific. Three of the six outstanding activities are close-out items: the magnetic separation technical handover, the water piping technical handover and the remaining electrical panel activity. The balance comprises completion of the spiral concentrator and the final equipment connections. Management is focused on closing these items, completing the spiral concentrator and executing the final equipment connections.

The Company recorded no lost time injuries or reportable safety incidents during the reporting period.

Operating Licence Workstreams

The previously granted installation licence (Licença de Instalação) (the “Installation Licence”) authorises the approved refurbishment and installation works at Azteca.

DEV has formally submitted its application for the Operating Licence to SEMA/AP. The application is now subject to technical review, which may include requests for additional information and a site inspection. Grant of the Operating Licence remains required before commercial operations and shipments can commence.

Next Milestones

Management’s immediate priority is to close the remaining technical handovers, complete the spiral concentrator and electrical panels and execute the final equipment connections. The programme continues to target 31 August 2026 for completion of the refurbishment works.

The next execution phase is integrated commissioning. This will test the completed systems together and establish whether the plant is ready to progress towards commercial operations. Commercial operations and shipments remain subject to successful commissioning, completion of the related regulatory workstreams and receipt of the Operating Licence.

Cadence Ownership

As of 31 May 2026, Cadence’s total investment in the Amapá Project was approximately US$16.1 million. Cadence holds a 36.2% equity interest in Pedra Branca Alliance Pte Ltd (“PBA”), which owns 100% of DEV Mineração S.A. (“DEV”), the owner and operator of the Amapá Project.

About the Amapá Project

The Amapá DR Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction (“DR“) grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, Azteca is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to successful commissioning, completion of related regulatory workstreams and receipt of the Operating Licence.

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608
Alan Green               

Qualified Person

Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.

Cautionary and Forward-Looking Statements

This announcement contains forward-looking statements. Such statements are based on the current expectations, assumptions and beliefs of the Directors and are subject to known and unknown risks and uncertainties. Forward-looking statements are not guarantees of future performance and may often be identified by words such as “believe”, “expect”, “intend”, “may”, “plan”, “should”, “will”, “could” and similar expressions. Actual results may differ materially from those expressed or implied by such statements due to a range of factors, many of which are outside the control of the Company, including changes in economic conditions, market conditions, regulatory developments, the actions of governmental authorities, the availability of funding and other risks affecting the Company’s operations. Readers should not place undue reliance on forward-looking statements, which speak only as at the date of this announcement. Except as required by law or applicable regulation, the Company undertakes no obligation to update or revise any forward-looking statements

Cadence Minerals #KDNC – Refurbishment progresses from 77% to 87%; completion target maintained

Cadence Minerals plc (AIM: KDNC) announces that refurbishment of the Azteca processing plant at the Amapá Iron Ore Project has progressed from 77% to 87% weighted physical completion since the Company’s announcement of 27 July 2026. The programme continues to target operational readiness by the end of August 2026. Commercial operations and shipments remain subject to successful commissioning and receipt of the Operating Licence

Highlights

  • Refurbishment on plan: Weighted physical completion has increased from 77% to 87%, matching planned progress. The 31 August 2026 completion target is unchanged.
  • Key processing circuits completed: The hopper/feed system, transfer conveyor, screen and process tank are complete. The spiral concentrator is approximately 64% complete against 50% planned.
  • Electrical execution advances: Electrical installation has increased from approximately 43% to 69% completion and is now in line with plan, materially advancing the principal execution focus identified in the previous update.
  • Remaining work concentrated: Magnetic separation has reached approximately 75% completion and is the principal processing workstream to close out.

Kiran Morzaria, Chief Executive Officer, commented:

“Execution is what matters. Azteca has moved from 77% to 87% completion and is now in line with plan.

Electrical installation was the principal execution focus in our previous update. It has advanced from 43% to 69% and is now in line with plan.

The remaining work is defined. Magnetic separation is the principal processing workstream to close, together with the remaining piping, concentrator and electrical activities.

Management’s priority is straightforward: complete the refurbishment against the 31 August target, move into commissioning and complete the regulatory workstreams required before commercial operations can commence.” 

Execution Update

The refurbishment programme is 87% complete against 87% planned, compared with 77% completion at the previous reporting date. Forty-nine of the 64 identified activities are now complete.

The hopper/feed system, transfer conveyor, screen and process tank are complete.

The spiral concentrator is approximately 64% complete against 50% planned, while piping is approximately 88% complete against 85% planned.

Electrical installation has advanced from approximately 43% to 69% completion and is now in line with plan. Electrical works were the principal remaining execution focus in the Company’s previous announcement.

Magnetic separation has reached approximately 75% completion and is now the principal processing workstream to close out. Two related activities, including technical handover, remain outstanding.

Management’s immediate priority is completion of magnetic separation and the remaining piping, concentrator and electrical activities, together with preparation for integrated plant commissioning.

The Company recorded no lost time injuries or reportable safety incidents during the reporting period.

Operating Licence Workstreams

The previously granted installation licence (Licença de Instalação) (the “Installation Licence”) authorises the approved refurbishment and installation works at Azteca. Commercial operations and shipments remain subject to receipt of the operating licence (Licença de Operação) (the “Operating Licence”). The Operating Licence process continues alongside completion of the refurbishment programme. DEV Mineração S.A. continues to engage with the State of Amapá Environmental Authority (SEMA/AP) and, as at the date of this announcement, the associated Operating Licence workstreams are progressing as expected.

Next Milestones

Management’s immediate focus is completion of the remaining plant close-out activities, including magnetic separation technical handover, outstanding water piping works, tank measurement and handover, completion and delivery of the spiral concentrator workstream, and final equipment connection and electrical completion. The current programme continues to target 31 August 2026 for completion of the refurbishment works.

Following completion of the refurbishment programme, the plant is intended to progress into integrated commissioning. Commercial operations and shipments remain subject to successful commissioning, completion of the related regulatory workstreams and receipt of the Operating Licence. The Pedra Branca do Amapári bridge, associated road works and additional Tailings Storage Facility works described in the Company’s announcements of 27 July 2026 and 5 August 2026 do not form part of the Azteca refurbishment programme, and there has been no change to the position set out in those announcements.

Cadence Ownership

As at the end of 31 May 2026, Cadence’s total investment in the Amapá Project is approximately US$16.1 million, representing a 36.2% equity stake.

About the Amapá Project

The Amapá DR Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction (“DR”) grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, Azteca is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to successful commissioning, completion of related regulatory workstreams and receipt of the LO.

 

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608
Alan Green               

Cadence Minerals #KDNC – Sonora Lithium Project; ICSID Arbitration Formally Registered

Cadence Minerals plc (AIM: KDNC) announces that the International Centre for Settlement of Investment Disputes (“ICSID”) has formally registered a Request for Arbitration filed by Cadence and its wholly owned subsidiary, REM Mexico Limited (“REM Mexico”), against the United Mexican States (“Mexico”) under the Agreement between the Government of the United Kingdom of Great Britain and Northern Ireland and the Government of the United Mexican States, which was signed on 12 May 2006 and entered into force on 25 July 2007 (“UK-Mexico BIT”).

The proceeding has been registered as Cadence Minerals Plc and REM Mexico Limited v. United Mexican States under ICSID Case No. ARB/26/36. The arbitration now moves to the constitution of the tribunal.

Highlights 

  • ICSID arbitration formally commenced: Cadence and REM Mexico’s claim against the United Mexican States has been registered as ICSID Case No. ARB/26/36, marking the formal commencement of an international arbitration between Cadence and REM Mexico and Mexico.
  • Tribunal constitution is the next step: The Parties will now proceed with the appointment of a three-member arbitral tribunal to hear Cadence and REM Mexico’s claims.
  • Cadence’s and REM Mexico seek compensation for Mexico’s conduct in relation to the Sonora Project: Cadence and REM Mexico’s claims relate to the cancellation by Mexico of the concessions comprising the Sonora Project and the resulting destruction of the value of Cadence and REM Mexico’s investments, which violated Mexico’s obligations under the UK-Mexico BIT, including the prohibition on unlawful expropriation, and Mexico’s obligations to accord fair and equitable treatment and full protection and security to Cadence and REM Mexico and not to discriminate against them.
  • Non-recourse funding supports the proceedings: Dedicated litigation funding from Litigation Capital Management (“LCM”) is in place to finance the legal fees and disbursements associated with the arbitration, preserving Cadence’s balance sheet flexibility.

Kiran Morzaria, Chief Executive Officer of Cadence Minerals, commented:

“Our objective is clear: we are seeking compensation for Mexico’s conduct in breach of the UK-Mexico treaty, which destroyed Cadence’s investments in the Sonora Project.

We are ably supported by an experienced specialist international arbitration team from Clifford Chance, and the claim is funded on a non-recourse basis, which will allow us to pursue the case without diverting capital from Cadence’s wider portfolio.

“We will remain disciplined, focus on execution and report material developments as the proceedings advance. It is disappointing that we have been left with no option but to seek compensation from Mexico by recourse to international arbitration. However, we are confident that we will ultimately secure a successful outcome.”

Background to the arbitration

Cadence first invested in the Sonora Lithium Project in 2013. Cadence and REM Mexico hold a 30% interest in Mexilit S.A. de C.V. and Minera Megalit S.A. de C.V., which held seven of the nine concessions forming part of the Sonora Project until Mexico cancelled all nine concessions in August 2023. It is the cancellation of those concessions and related conduct by Mexico for which Cadence and REM Mexico are challenging in the arbitration.

In particular, Mexico’s conduct breached its obligations under the UK-Mexico BIT, including those relating to:

  • unlawful nationalisation or expropriation;
  • fair and equitable treatment and full protection and security; and
  • national treatment and most-favoured nation treatment.

Cadence and REM Mexico are seeking compensation and other relief in respect of these breaches of the UK-Mexico BIT.

There can be no certainty as to the outcome, duration or level of any recovery from the arbitration.

Next steps in the arbitration

The next stage is the constitution of the three-member arbitral tribunal. Each party will appoint one arbitrator, with the parties then seeking to agree on the tribunal chair.

Once constituted, the tribunal will establish the procedural timetable for the proceeding. Cadence will report further material developments as appropriate.

Arbitration funding

As announced on 24 March 2026, LCM is providing non-recourse finance for the arbitration.

LCM will fund legal fees and disbursements arising in connection with the arbitration. If the claims do not succeed and no recovery is made, Cadence and REM Mexico are not required to repay the funded amounts, subject to the agreement.

This enables the arbitration to proceed without diverting capital from Cadence’s wider portfolio.

Notwithstanding the arbitration, Cadence and REM Mexico remain open to a negotiated resolution with Mexico.

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608
Alan Green               

Cautionary and Forward-Looking Statements

This announcement contains forward-looking statements. Such statements are based on the current expectations, assumptions and beliefs of the Directors and are subject to known and unknown risks and uncertainties. Forward-looking statements are not guarantees of future performance and may often be identified by words such as “believe”, “expect”, “intend”, “may”, “plan”, “should”, “will”, “could” and similar expressions. Actual results may differ materially from those expressed or implied by such statements due to a range of factors, many of which are outside the control of the Company, including changes in economic conditions, market conditions, regulatory developments, the actions of governmental authorities, the availability of funding and other risks affecting the Company’s operations. Readers should not place undue reliance on forward-looking statements, which speak only as at the date of this announcement. Except as required by law or applicable regulation, the Company undertakes no obligation to update or revise any forward-looking statements.

Cadence Minerals #KDNC – Refurbishment progresses from 48% to 77%; operational readiness target maintained

Cadence Minerals plc (AIM: KDNC) is pleased to announce that refurbishment of the Azteca processing plant at the Amapá Iron Ore Project has progressed from 48% to 77% weighted physical completion since the Company’s previous operational update and continues to run ahead of schedule, exceeding the planned 72% completion at the reporting date.

Highlights

  • Refurbishment continues ahead of plan: Weighted physical completion has increased from 48% to 77% since the previous operational update, exceeding planned progress and maintaining the targeted operational readiness schedule. The Company continues to target operational readiness by the end of August 2026.
  • Key processing circuits nearing completion: The hopper, transfer conveyor and process tank installation have been completed, while screen refurbishment is approximately 98% complete, progressively reducing execution risk across the processing plant.
  • Critical workstreams progressing: Magnetic separation has reached approximately 69% completion and electrical installation approximately 43% completion, with electrical works representing the principal remaining execution focus.
  • Metallurgical programme completed: Test work has confirmed the proposed processing flowsheet for production of approximately 65% Fe iron ore concentrate from feed material grading approximately 48% Fe, establishing the operating parameters for commissioning.
  • Operating Licence workstreams continue: Installation Licence workstreams continue to progress as planned. Commercial operations and shipments remain subject to receipt of the Operating Licence.

Kiran Morzaria, Chief Executive Officer, commented:

“Projects create value through execution. Advancing from 48% to 77% completion while remaining ahead of schedule demonstrates that the Azteca refurbishment is moving through its critical execution phase as planned.

With the metallurgical programme complete, the technical pathway to commissioning is now established. Our focus is increasingly shifting from rebuilding the plant to preparing it for reliable operations, while refining the infrastructure required to support long-term production.

Management’s priority is straightforward: complete the remaining execution work, secure the Operating Licence and transition Azteca into commercial operations. Achieving that will establish the first operating platform within the wider Amapá Project and position the Company for its next phase of development.” 

Execution Update

The refurbishment programme continues to perform ahead of the approved execution schedule. Weighted physical completion has increased from 48% to 77%, compared with planned progress of 72%, with 43 of the 64 identified work packages now complete.

Completion of the principal mechanical workstreams has progressively shifted the execution focus towards electrical installation, integrated commissioning and Operating Licence readiness. The feed hopper, transfer conveyor and process tank installation have been completed, while screen refurbishment is substantially complete.

Electrical installation remains the principal execution activity during the final phase of refurbishment. Management’s immediate priority is completion of the remaining electrical systems, commissioning of the magnetic separation circuit and preparation for integrated plant commissioning.

The Company recorded no lost time injuries or reportable safety incidents during the reporting period.

Technical Update

The planned metallurgical programme has been completed. The programme confirmed the proposed processing flowsheet required to produce approximately 65% Fe iron ore concentrate from the planned feed material and established the operating parameters for commissioning.

The test work demonstrated approximately 53% mass recovery and 72.8% iron recovery, with feed material grading approximately 48% Fe required to achieve the target concentrate specification.

Completion of the programme provides technical validation of the proposed processing route and further reduces execution risk ahead of commissioning

Infrastructure and Funding

As engineering work has progressed, the Company has refined the infrastructure required to support sustained commercial operations.

These requirements principally comprise road infrastructure together with additional Tailings Storage Facility (“TSF”) works identified following completion of the dam break assessment. These infrastructure requirements are separate from the Azteca refurbishment programme and do not affect the Company’s current refurbishment activities or targeted operational readiness.

The existing prepayment facility continues to fund refurbishment and commissioning of the Azteca plant. The Company is assessing the scope, timing and funding of these longer-term infrastructure investments and will provide further updates as those assessments progress.

Operating Licence Workstreams

The Installation Licence authorises the approved refurbishment and installation works at Azteca. Commercial operations and shipments remain subject to receipt of the Operating Licence.

The Operating Licence process continues to progress alongside completion of the refurbishment programme. Environmental monitoring, environmental management and implementation of the applicable licence conditions continue in accordance with the approved work programme.

DEV Mineração S.A. continues to engage with the State of Amapá Environmental Authority (SEMA/AP) and, as at the date of this announcement, the associated Operating Licence workstreams are progressing as expected.

Next Milestones

Management’s immediate focus is completion of the remaining electrical installations, integrated plant commissioning and completion of the Operating Licence workstreams.

Subject to successful commissioning and receipt of the Operating Licence, the Company continues to target operational readiness by the end of August 2026.

The refurbishment programme continues to be undertaken under the previously granted Installation Licence. Commercial operations and shipments remain subject to receipt of the Operating Licence.

Cadence Ownership

As at the end of 31 May 2026, Cadence’s total investment in the Amapá Project is approximately US$16.1 million, representing a 36.2% equity stake.

About the Amapá Project

The Amapá DR Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction (“DR”) grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, Azteca is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to successful commissioning, completion of related regulatory workstreams and receipt of the LO.

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608
Alan Green               

Qualified Person

Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.

Cautionary and Forward-Looking Statements

This announcement contains forward-looking statements. Such statements are based on the current expectations, assumptions and beliefs of the Directors and are subject to known and unknown risks and uncertainties. Forward-looking statements are not guarantees of future performance and may often be identified by words such as “believe”, “expect”, “intend”, “may”, “plan”, “should”, “will”, “could” and similar expressions. Actual results may differ materially from those expressed or implied by such statements due to a range of factors, many of which are outside the control of the Company, including changes in economic conditions, market conditions, regulatory developments, the actions of governmental authorities, the availability of funding and other risks affecting the Company’s operations. Readers should not place undue reliance on forward-looking statements, which speak only as at the date of this announcement. Except as required by law or applicable regulation, the Company undertakes no obligation to update or revise any forward-looking statements

Cadence Minerals #KDNC – Azteca Execution Update

Cadence Minerals plc (AIM: KDNC) announces that refurbishment works at the Azteca plant, part of the Amapá Iron Ore Project in Brazil, are ahead of the current works schedule.

The refurbishment programme had reached approximately 48% weighted physical progress, compared with 41% planned progress. The Company continues to target operational readiness by the end of August 2026, subject to completion of the remaining refurbishment, electrical installation, equipment connection, commissioning preparation and technical handover activities.

Commercial operations and shipments remain subject to receipt of the Operating Licence (“LO”). The related LO workstreams continue to progress as expected.

Highlights

  • Refurbishment ahead of plan: Azteca had reached approximately 48% weighted physical progress as at 2 July 2026, compared with 41% planned progress.
  • Works programme advancing: The current schedule tracks 64 activities, of which 21 have been completed, 10 are in progress and 33 have not yet started.
  • Key processing areas advanced: The hopper is approximately 83% complete, the conveyor system is approximately 79% complete and the screen is approximately 69% complete.
  • Critical workstreams remain: Magnetic separation is approximately 35% complete and the electrical system is approximately 23% complete.
  • Operating Licence workstreams continue: Commercial operations and shipments remain subject to receipt of the Operating Licence, with the related LO workstreams progressing as expected.

Kiran Morzaria, Chief Executive Officer of Cadence, commented:

“Azteca has moved from planning into measurable site execution. The current progress is encouraging and reflects the benefit of the preparation completed before mobilisation.

The plant is now advancing through the workstreams that matter: refurbishment, electrical installation, operational readiness and the regulatory pathway to commercial operations.

Azteca remains the practical first step in bringing Amapá back into production. The focus is on disciplined delivery, schedule control and converting execution progress into the operating platform for the wider project.” 

Current Status

The Azteca restart programme is being carried out under the approved refurbishment and installation programme authorised by the Installation Licence.

The current works schedule tracks 64 activities across the plant, including mobilisation, feed preparation, conveyors, screens, magnetic separation, spiral concentration, piping, tanks and electrical systems. As at 2 July 2026, 21 activities had been completed, 10 were in progress and 33 had not yet started.

The Company measures the refurbishment programme using weighted physical progress. This takes account of the relative size and importance of each activity and provides a clearer view of execution progress than a simple count of completed tasks.

On this basis, Azteca had reached 47.8% weighted physical progress as at 2 July 2026, compared with planned progress of 41.0%.

The Company continues to target operational readiness by the end of August 2026. This remains subject to completion of the remaining works and no material slippage in the remaining critical activities.

Progress by Area

The hopper, conveyor system and screen are the most advanced areas of the plant. The hopper is 82.9% complete. The conveyor system is 78.9% complete. The screen is 68.8% complete.

These areas include completed or advanced work relating to access, mechanical inspection, structural alignment, component refurbishment and industrial painting.

Magnetic separation is 35.0% complete and remains an important processing workstream. Electrical works remain a key workstream before operational readiness. The electrical system is 22.7% complete. Panel dismantling and lighting dismantling have been completed. Motor testing associated with the screen is underway.

Schedule Status

The current works status does not change the Company’s target for Azteca to be operationally ready by the end of August 2026.

Operational readiness remains subject to completion of the remaining refurbishment activities, electrical installation, equipment connection, commissioning preparation and technical handover activities.

Management has not identified any material schedule slippage against the current works programme as at the date of this announcement. Commercial operations and shipments remain subject to receipt of the LO and completion of the related regulatory workstreams.

Operating Licence Workstreams

The Installation Licence authorises the approved refurbishment and installation works at Azteca. It does not authorise commercial operations or shipments. The Operating Licence (“LO”) remains the regulatory approval required before commercial operations and shipments can commence.

The LO is assessed following completion of the relevant installation works and demonstration that the applicable Installation Licence conditions have been satisfied. These conditions include environmental monitoring, environmental management and implementation of applicable environmental control plans.

DEV Mineração S.A. (“DEV”) continues to progress the LO process with the State of Amapá Environmental Authority, Secretaria de Estado do Meio Ambiente (“SEMA/AP”). Several of the workstreams required to support the LO process are being undertaken during alongside the installation of the Azteca plant.

As at the date of this announcement, these workstreams are progressing as expected.

Strategic Context

Azteca remains Cadence’s near-term operational focus within the staged redevelopment strategy for Amapá.

Subject to successful completion of refurbishment works, commissioning activities, completion of the related regulatory workstreams and receipt of the LO, Azteca is intended to establish the first operating platform at Amapá.

The broader Amapá development remains subject to further technical studies, financing, construction planning and regulatory approvals.

Cadence Ownership

As of the end of 31 May 2026, Cadence’s total investment in the Amapá Project is approximately £14.13 million, representing a 36.2% equity stake.

About the Amapá Project

The Amapá DR Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction (“DR”) grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, Azteca is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of approximately 65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to successful commissioning, completion of related regulatory workstreams and receipt of the LO.

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608
Alan Green               

Cadence Minerals #KDNC – Annual Results for the year ended 31 December 2025

Cadence Minerals (AIM: KDNC) is pleased to announce its final results for the year ending 31 December 2025. The full Annual Report and Audited Financial Statements will be available on the Company’s website at https://www.cadenceminerals.com/  and will be posted to shareholders shortly.

Chairman’s Statement

Dear Shareholders,

I present the Company’s Annual Report and Audited Financial Statements for the year ended 31 December 2025.

The year under review was one of measured progress for Cadence, set against continued uncertainty in commodity and capital markets. The Company remained pre-production at year end, and I recognise that progress has taken longer than shareholders would have wished. During the year the Board made one important strategic decision. Rather than pursuing the full redevelopment of Amapá as a single project, we prioritised Azteca as the first operating stage. That decision reduced initial capital requirements and established a more practical route toward operating cash flow.

Commodity conditions were mixed. Iron ore proved relatively resilient, particularly where product quality was higher, while lithium experienced a more pronounced correction. These cycles are part of the sector. The Board’s response was to concentrate capital on assets with clearer near-term value drivers and to maintain financial discipline. On those measures, I believe Cadence ended the year in a stronger position than it began.

For reporting purposes, Amapá is presented as two related stages: Azteca, the near-term restart project, and the Amapá DR Project, the larger redevelopment opportunity. 

During the year, Cadence completed several defined Azteca milestones. We defined the production plan, agreed heads of terms for a prepayment offtake structure and subsequently executed a binding agreement. Cadence funded its participation in the Azteca restart through equity while the balance of project funding is provided through the binding prepayment offtake structure. The Board remains mindful of dilution; however, this funding enabled the Company to maintain momentum at a critical stage of the Azteca restart and moved the project from planning toward refurbishment.

At the period end, Azteca had a defined production plan, secured funding structure and identified feed material. Commercial production remained dependent upon completion of refurbishment, commissioning and receipt of the Operating Licence. For the Amapá DR Project, work during the year strengthened the longer-term development case, including reductions in projected mining costs. This was a significant achievement, improving the cost framework for the larger development while preserving the pathway toward a 5.5 Mtpa direct reduction grade operation. That development remains dependent on further technical work, financing and regulatory approvals.

Post-period, Azteca received both the Preliminary Environmental Licence and Installation Licence. These approvals allow execution of the approved refurbishment programme and represent an important step in the restart pathway. The remaining critical-path items are refurbishment, commissioning and receipt of the Operating Licence required before commercial operations can commence.

The Sonora Lithium Project remained subject to concession cancellation and legal proceedings. No operational progress was recorded during the year, and the Company’s focus remains on pursuing legal remedies. Post period, non-recourse litigation funding was made available to support the Company’s claims, subject to the terms of the relevant funding agreement.

Cadence has stated its intention to pursue claims under the UK-Mexico BIT. This provides a funded route to pursue the claim, although the timing and outcome of the arbitration process remain uncertain.

Looking ahead, Cadence enters the new financial year with a defined set of near-term milestones at Amapá. The immediate priority is to complete Azteca refurbishment, commission the plant and obtain the Operating Licence. Subject to completion of refurbishment, commissioning activities, satisfaction of licence conditions and receipt of the required operating approvals, Azteca is intended to provide the initial step toward production. 

Progression of the Amapá DR Project will continue in parallel, but remains dependent on further study, financing and regulatory approvals. The Board’s priority is straightforward: complete the Azteca restart steps, preserve funding flexibility and maintain risk control.

Finally, I would like to thank my fellow Board members, our partners and advisers, and all shareholders for their continued support and patience during the year.

Andrew Suckling

Non-Executive Chairman

26 June 2026

 

For further information, contact:

 

Cadence Minerals plc

+44 (0) 20 3582 6636

Andrew Suckling

Kiran Morzaria

Zeus (NOMAD & Broker)

+44 (0) 20 3829 5000

James Joyce

Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker

+44 (0) 20 3411 7773

Guy Wheatley

Public & Investor Relations – Brand Communications

+44 (0) 7976 431608

Alan Green           

Qualified Person

Kiran Morzaria B.Eng. (ACSM), MBA, has reviewed and approved the information contained in this announcement. Kiran holds a Bachelor of Engineering (Industrial Geology) from the Camborne School of Mines and an MBA (Finance) from CASS Business School.

Cautionary and Forward-Looking Statements

Certain statements in this announcement are or may be deemed to be forward-looking statements. Forward-looking statements are identified by their use of terms and phrases such as “believe”, “could”, “should”, “envisage”, “estimate”, “intend”, “may”, “plan”, “will”, or the negative of those variations or comparable expressions including references to assumptions. These forward-looking statements are not based on historical facts but rather on the Directors’ current expectations and assumptions regarding the company’s future growth results of operations performance, future capital, and other expenditures (including the amount, nature, and sources of funding thereof) competitive advantages business prospects and opportunities. Such forward-looking statements reflect the Directors’ current beliefs and assumptions and are based on information currently available to the Directors.  Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements, including risks associated with vulnerability to general economic and business conditions, competition, environmental and other regulatory changes actions by governmental authorities, the availability of capital markets reliance on key personnel uninsured and underinsured losses and other factors many of which are beyond the control of the company. Although any forward-looking statements contained in this announcement are based upon what the Directors believe to be reasonable assumptions. The company cannot assure investors that actual results will be consistent with such forward-looking statements.

Chief Executive Officer’s Commentary

At the beginning of 2025, Amapá had a clear technical case but an uncertain route to production. During the year we changed the development sequence. We prioritised Azteca because it provides a lower-capital route to initial production and the opportunity to establish operating cash flow before committing capital to the larger Amapá DR Project. Those steps did not eliminate execution risk, but they reduced uncertainty around how the project moves toward operations.

Timelines did move. Additional regulatory and technical work was required, particularly around archaeological clearance, water-related approvals and tailings permitting. This extended the path to commissioning beyond earlier expectations. These items extended the timetable and increased the importance of disciplined cash and funding management during the restart phase. The important distinction is that, over the period and post-period, the nature of the remaining risk changed. The workstreams became more defined, the regulatory pathway narrowed, and the immediate focus moved from project definition to execution readiness.

Post-period, receipt of the Preliminary Environmental Licence and Installation Licence completed the principal permitting milestones required before execution of the refurbishment programme. These approvals do not remove all remaining risk. Azteca still requires licence-compliant refurbishment, commissioning and receipt of the Operating Licence before commercial operations can commence.

The objective remains straightforward: complete refurbishment, commissioning and operating approval, establish Azteca as the first operating platform at Amapá and, subject to successful execution, use that platform to support the broader Amapá development pathway. 

Executive Summary

·    We prioritised Azteca as the first operating phase within the Amapá development strategy.

·    We established the funding and regulatory pathway required to move Azteca into refurbishment.

·    Post-period, refurbishment commenced following receipt of the Preliminary Environmental Licence and Installation Licence.

·    The remaining critical-path items are refurbishment, commissioning and receipt of the Operating Licence required before commercial operations.

·    Capital was directed toward activities expected to shorten the path to first production rather than expanding project scope.

·    The commissioning timetable moved beyond the earlier end-June 2026 target, extending the period before Azteca is expected to contribute operating cash flow.

·    We advanced Sonora into a funded arbitration process, moving it into a legal recovery track. 

What Changed During the Year

Strategy changed from full redevelopment to staged restart | At the start of the year, Amapá was technically defined but still broad in scope and dependency. By year end, the focus had narrowed to Azteca and the steps required to restart operations.

Regulatory uncertainty reduced | Licensing took longer than expected. However, the remaining work became better defined, with a clearer regulatory pathway and fewer unknowns.

Funding aligned to development milestones | We moved away from a single large funding requirement toward a staged approach, with Azteca funded through a defined structure linked to milestones.

Capital and management focus concentrated on Amapá | The Company’s effort is now concentrated on Amapá. Other assets are being managed appropriately, but near-term delivery is focused on Amapá.

Amapá Iron Ore Project

The Amapá Project remains the cornerstone of Cadence’s strategy. The immediate focus is Azteca. The larger Amapá DR Project remains the longer-term redevelopment opportunity. For clarity, Amapá should now be considered as two related but distinct development projects.

Azteca is the near-term restart project. It is based on the refurbishment of the existing plant and the processing of already mined or partly processed material stored on site. Its purpose is to create the first operating platform at Amapá, subject to completion of works, commissioning and operating approval.

The Amapá DR project is the larger, long-term redevelopment project. It is based on the mine, beneficiation plant, rail and port infrastructure and targets production of 5.5 Mtpa of DR-grade concentrate. It remains subject to further studies, financing, infrastructure work and additional approvals.

Azteca is not a substitute for the larger Amapá DR project. It is the first stage in the pathway toward it. During the year, Azteca progressed from concept toward an execution-ready project. It now has a defined feed source, production plan and funding framework, subject to completion of the remaining steps required for operation. These include licence-compliant works, plant refurbishment, commissioning and the receipt of the relevant operating licence.

The larger Amapá DR project continues to be supported by prior technical work, including the updated PFS and cost optimisation initiatives. During the period, revised mining cost assumptions improved the project’s cost position. However, progression of this larger project remains dependent on further studies, financing and additional approvals.

Subject to successful commissioning, Azteca is intended to establish the Company’s first operating cash flow and provide a platform from which the broader DR Project can be advanced.

Funding and Capital Structure

A key development during the year was the establishment of a binding funding structure for Azteca.

The Company entered into a binding prepayment offtake arrangement to support the restart of the plant, together with securing its own participation funding. This structure is intended to fund licensing, refurbishment, commissioning and initial working capital requirements, while reducing, but not eliminating, the need for additional equity funding.

The objective was to fund only those activities that moved Azteca closer to production while limiting further shareholder dilution.

Current Status

At the date of approval of this report, Azteca has moved beyond project definition and permitting into execution. Mobilisation has been completed; refurbishment activities are underway and execution workstreams are progressing across the plant. The commissioning timetable moved beyond the earlier targeted end-June 2026 date and is now dependent on completion of the refurbishment programme, commissioning works and receipt of the Operating Licence required before commercial operations can commence. In parallel, DEV continues to assess infrastructure, environmental and operational readiness requirements associated with the transition toward commercial operations.

The principal milestones that remain are execution of the refurbishment programme, successful commissioning and receipt of the Operating Licence. Subject to successful completion of these activities, Azteca is intended to become the first operating stage within the broader Amapá development strategy.

Sonora Lithium Project

Cadence continues to hold a 30% interest in the Sonora Lithium Project. During the period, Sonora remained subject to concession cancellation and associated legal proceedings. There was no change to the operational status of the project. 

Subsequent to the period end, arbitration funding was secured, providing access to non-recourse funding to support the Company’s legal claims, subject to the terms of the funding arrangements. Any outcome remains dependent on legal process and determination.

Risk and Outlook

The Company’s principal risks are now operational rather than developmental. The key remaining milestones are completion of refurbishment, commissioning and receipt of the Operating Licence.

Additional environmental, tailings, infrastructure or operating requirements may arise during refurbishment and commissioning. These could increase costs, defer first production or require additional funding.. Delays to commissioning or ramp-up would defer the point at which Azteca contributes operating cash flow and may increase the Company’s reliance on additional equity funding.

At Sonora, risks relate to the outcome and duration of legal proceedings.

Looking ahead, the Company’s immediate priority is to progress Azteca through refurbishment, commissioning and operating approval, subject to completion of the required steps. Beyond this, the focus remains on advancing the longer-term Amapá DR Project in a disciplined manner. The priorities are clear: complete refurbishment, commission the plant, obtain the Operating Licence and establish operating cash flow.

Kiran Morzaria

Chief Executive Officer

26 June 2026

Full financial statements here

Cadence Minerals #KDNC – Azteca Execution Update

Mobilisation Completed and Refurbishment Programme Remains on Schedule

Cadence Minerals plc (AIM: KDNC) announces that mobilisation of the Azteca restart programme at the Amapá Iron Ore Project in Brazil has been completed and refurbishment works are underway across the principal processing, infrastructure and electrical workstreams.

Execution activities are progressing on schedule against the current refurbishment programme, advancing the project toward commissioning and operational readiness.

Highlights

  • Mobilisation of personnel, equipment and site resources completed on schedule, enabling execution of the approved refurbishment programme.
  • Refurbishment activities are underway across the principal processing and electrical systems, progressing the project toward commissioning.
  • Execution activities remain on schedule against the current programme, with no material slippage reported.
  • Based on progress to date, the Company expects the Azteca plant to be operationally ready by the end of August 2026. Commencement of commercial operations remains subject to receipt of the Operating Licence (“LO”).

Kiran Morzaria, Chief Executive Officer of Cadence, commented:

“The significance of the progress made since receipt of the Installation Licence is not simply that refurbishment activities have started. It is that the project has transitioned from planning into delivery.

Mobilisation is complete, contractors are active on site and progress is increasingly being measured against execution, commissioning and operational readiness milestones.

Our focus remains on completing the refurbishment programme safely, maintaining schedule discipline and progressing the requirements necessary to support operational readiness and commercial operations.”

Execution Progress

The Azteca restart programme is being executed under the approved refurbishment and installation programme authorised by the Installation Licence.

Mobilisation activities were completed on schedule, including deployment of personnel, equipment, lifting resources and refurbishment materials to site.

Refurbishment works are progressing across key processing systems, including plant feeding and magnetic separation. Electrical works have also commenced and remain the critical-path activity within the execution programme.

Activities completed or underway include structural inspections, access rehabilitation, equipment inspection, refurbishment of mechanical components, electrical panel works and associated infrastructure preparation.

The remaining workstreams principally comprise completion of refurbishment activities, electrical installation, equipment connection and commissioning activities.

With the Installation Licence granted, funding received and mobilisation completed, the principal focus of the project has shifted toward execution, commissioning and operational readiness.

As at the date of this announcement, management has not identified any material schedule slippage against the current execution programme, the Company expects the Azteca plant to be operationally ready by the end of August 2026. Commencement of commercial operations remains subject to receipt of the LO.

Operational Readiness

Alongside physical refurbishment activities, the Company and its JV partners continue to advance operational readiness activities required to support future commercial operations.

These activities include environmental compliance workstreams, operational planning and preparation for commissioning activities.

The Company and its JV partners continue to assess infrastructure, environmental and operational requirements associated with the transition to commercial operations. These assessments form part of the ongoing preparation required to support future commissioning and commercial operations.

Strategic Context

The Azteca Project remains the first operational phase within the broader Amapá development strategy.

Subject to successful completion of refurbishment works, commissioning activities and receipt of the Operating Licence, Azteca is intended to establish an initial operating platform from which the JV partners can evaluate subsequent development opportunities across the wider Amapá Project.

Cadence Ownership

As of the end of March 2026, Cadence’s total investment in the Amapá Project is approximately US$16.1 million, representing a 36.2% equity stake.

About the Amapá Project

The Amapá DR Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on the 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction (“DR”) grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, the Azteca Project is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of ~65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to permitting.

 

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608

Cadence Minerals #KDNC – Azteca Restart Update

Cadence Minerals plc (AIM: KDNC) announces an update regarding the restart of the Azteca Plant at the Amapá Iron Ore Project in Brazil.

Highlights 

  • Installation Licence (“LI”) was granted by SEMA/AP and announced on 5 May 2026, authorising approved refurbishment and installation works at Azteca.
  • Following grant of the LI, the offtaker requested clarification on the LI / Operating Licence (“LO”) sequencing and construction funding tranches. Clarification documentation was agreed, and the first construction funding tranche was cleared on the 25 May 2026.
  • DEV has executed the primary contractor agreement, with mobilisation activities expected to commence next week and full contractor mobilisation expected during the second week of June 2026.
  • The previous end-June commissioning target was based on an approximately 90-day restart programme from the originally anticipated licence timing, including operational contingency.
  • Due to a combination of the licensing timeline and the request for clarification by the offtaker, commissioning activities are now expected approximately 60 days from receipt of the first construction funding tranche on 25 May 2026 under an accelerated schedule, or approximately 90 days from that date where normal operational contingency is incorporated.

Kiran Morzaria, Chief Executive Officer of Cadence, commented:

“Having just returned from site, I remain encouraged by the practical progress being made at Azteca and the level of operational readiness across the project. 

During the visit, I worked closely with our JV partners and technical teams reviewing execution scheduling, critical path activities and operational readiness planning, including recruitment of key operational personnel and implementation of site control systems.

With the LI granted, funding now progressing and contractor mobilisation expected to commence shortly, Azteca recommissioning is progressing rapidly into the execution phase.”

Current Status

The LI granted by SEMA/AP authorises the approved refurbishment, construction and installation works associated with the Azteca restart programme.

Due to a combination of the licensing timeline and the above request for clarification by the offtaker and based on the current execution schedule, commissioning activities are now expected approximately 60 days from receipt of the first construction funding tranche on 25 May 2026 under an accelerated schedule, or approximately 90 days from that date where normal operational contingency is incorporated, subject to completion of the approved works and receipt of the LO.

DEV has executed the primary contractor agreement and expects mobilisation activities to commence next week with full contractor mobilisation expected during the second week of June 2026.

Execution Programme

As previously disclosed, management’s end-June commissioning target was based on anticipated receipt of the LI by the end of March 2026 and an approximately 90-day execution programme which incorporated operational contingency for execution slippage or unplanned works.

The LI was granted later than originally anticipated at the end of April, materially utilising the operational contingency previously built into the programme. DEV and Cadence continued to believe the end-June commissioning target remained achievable following receipt of the LI under an accelerated execution programme.

The additional time required to finalise the clarification documentation means that, based on the current execution schedule, DEV currently expects commissioning activities approximately 60 days from receipt of the first construction funding tranche on 25 May 2026 under an accelerated schedule, or approximately 90 days from that date where normal operational contingency is incorporated. This subject to normal satisfaction of applicable LI conditions and receipt of the LO for commercial operations. Accordingly, given the licensing timeline and the request for clarification by the offtaker, the stated commissioning target for end June 2026 has now moved to end of July under an accelerated development timeline and end of August 2026, if we include normal contingencies.

Licensing and Remaining Approvals

In accordance with the standard Brazilian environmental licensing sequence, an LO is required for commercial operations and is expected to be granted following completion of the approved construction and refurbishment works authorised under the LI and implementation of the relevant operational and environmental control measures.

Progression toward the LO has already commenced and will focus principally on demonstrating compliance with the applicable LI conditions and operational readiness requirements, rather than a new project design approval process.

The Company will provide further updates as mobilisation progresses.

Cadence Ownership

As of the end of March 2026, Cadence’s total investment in the Amapá Project is approximately US$16.1 million, representing a 36.2% equity stake.

About the Amapá Project

The Amapá Iron Ore Project is a fully integrated iron ore operation in Brazil with established mine, rail, port and beneficiation infrastructure. The Project hosts a JORC-compliant Mineral Resource of 276 million tonnes at 38% Fe and a Proven and Probable Ore Reserve of 195.8 million tonnes at 39.34% Fe.

An updated Pre-Feasibility Study published on the 3 December 2024 confirmed the potential to produce 67.5% Fe direct reduction (“DR”) grade concentrate at 5.5 Mtpa, with a post-tax NPV (10%) of US$1.97 billion over a 15-year mine life.

As part of a staged redevelopment strategy, the Azteca Project is intended to be recommissioned as the initial production facility, targeting approximately 380,000 tonnes per annum of ~65% Fe concentrate from existing tailings. This initial production is intended to generate early cash flow to support ongoing operations and the broader development of the Project, subject to permitting.

For further information, contact:

 

Cadence Minerals plc +44 (0) 20 3582 6636
Andrew Suckling
Kiran Morzaria
Zeus (NOMAD & Broker) +44 (0) 20 3829 5000
James Joyce
Darshan Patel

Chris Wardley

Fortified Securities – Joint Broker +44 (0) 20 3411 7773
Guy Wheatley
Public & Investor Relations – Brand Communications +44 (0) 7976 431608
Alan Green               

Cadence Minerals #KDNC – CEO Kiran Morzaria talks to Alan Green

Alan Green talks to Kiran Morzaria, CEO at AIM listed Cadence Minerals #KDNC which owns a 36% stake in the Amapa iron ore project in Brazil. The Company has just received the Installation Licence from the State of Amapá Environmental Authority which authorises refurbishment, construction and installation works for the Azteca Plant and the larger Amapá Project, worth $1.9bn NPV. Kiran discusses the significance of the licence award and the resulting shift from planning to engineers on the ground preparing Azteca for restart. We look at the impact that the Iran War and closing of the Strait of Hormuz have had on global markets, and the resilience of the iron ore price, before discussing fundraising and the funding picture longer term for Amapa. We also look at the Sonora Lithium Project, where LCM Funding have provided non-dilutive funding to prosecute the Mexican Govt, before ending with near term milestones in the run up to first production at Azteca.

I would like to receive Brand Communications updates and news...
Free Stock Updates & News
I agree to have my personal information transfered to MailChimp ( more information )
Join over 3.000 visitors who are receiving our newsletter and learn how to optimize your blog for search engines, find free traffic, and monetize your website.
We hate spam. Your email address will not be sold or shared with anyone else.